Ruskin Mill Trust
Location
Sunfield Garden School & Children's Homes
Clent Grove
Woodman Lane
Stourbridge
West Midlands
Phase 1
SCI assessed whether removing the 1950s-era overhead power cables was feasible for the Sunfield Garden School Overhead Cable Removal Project.
As a result, the remodel required removing the poles.
The client consulted a local electrical engineering firm, but the firm felt the project was beyond its capabilities.
As a result, we conducted a three-day site survey to determine the requirements for installing new underground cables to maintain power throughout the site.
The survey involved entering each property to assess the load requirements.
All 10 properties are currently supplied by the overhead cables.
Additionally, we used the information to calculate the total load demand.
We completed the necessary load balancing for each phase.
We designed a new system to enable the installation of SWA armoured cables below.
The red dots represent the current locations of the poles.
Moreover, they support four overhead cables carrying three phases, neutral, and earth around the facility.
Phase 2
Due to permanent residents at the children's home, this is part of the Sunfield Garden School | Overhead Cable Removal Project. Additionally, officials provided a four-hour window to disconnect the poles' power and reconnect properties to underground cables for the project.
Buildings B1, B2, and B3 house permanent residents.
Therefore, they required uninterrupted power after the existing supply was isolated and removed.
To facilitate this critical changeover, we installed cabinets throughout the site. Additionally, we ran cables to each cabinet below ground, as well as to the respective properties.
Phase 3
Firstly, once the above properties were re-energised, we proceeded to run the appropriate cables to each cabinet location.
We then ran cables to the respective buildings.
During this phase, we were asked to power the car park to allow EV charger installation later.
The power supply to the properties was already at its maximum load.
Additionally, to address this, we ran a new cable from the plant room to the car park.
We also constructed a plinth to mount an additional cabinet for future use.
Final results from the load balancing calculations:
| 60% Concurrent Usage | ||||
| Phase 1 | Phase 2 | Phase 3 | Cab ID | |
| B1 | 38 | 38 | 38 | 1 |
| B2 | 30 | 2 | ||
| B3 | 38 | 38 | 38 | 2 |
| B4 | 30 | 30 | 30 | 1 |
| B5 | 30 | 3 | ||
| B6 | 30 | 30 | 30 | 3 |
| B7 | 30 | 4 | ||
| B8 | 30 | 4 | ||
| B9 | 30 | 4 | ||
| B10 | 30 | 4 | ||
| Amps | 196 | 196 | 196 | |